Items
|
Original |
Establishment of PMU |
May ,2011 |
Selection of Consultants |
June 2011 to Sept 2012 |
Capacity Development of PMU staff on PDCA Cycle |
Aug 2011 to Dec 2017 |
Development of MIS & GIS System |
Feb.2012– Nov. 2013 |
Preparation of extension material |
Nov. 2011 to Nov. 2014 |
Training for community motivators |
June 2012 to Jan. 2016 |
Baseline Survey |
June,2012 |
Mid-term impact assessment |
September,2015 |
Terminal impact assessment |
January,2018 |
Organization of farmers groups |
Feb 2012 – Sept. 2015 |
Training on vegetable cultivation |
Jan. 2012 – March 2018 |
Training on food grains cultivation |
Jan. 2012 – March2018 |
Promotion of post-harvest technology |
Jan. 2012 – March2018 |
First-Priority Sub-projects |
June-12– Sep.. 2013 |
Second-Priority Sub-projects |
Oct. 2012 – Feb 2014 |
Third-Priority Sub-projects (1st batch) |
Oct. 2013 – Sept. 2015 |
Third-Priority Sub-projects (2nd batch) |
Aug. 2014 – Aug 2016 |
Third-Priority Sub-projects (3rd batch) |
July 2015 – Aug 2017 |
Project Completion Date* |
March 2018 |
* Extended till December 2020.