Indicative Project Time Scale

Last Updated On: 29/06/2017

Items    Original
Establishment of PMU May ,2011
Selection of Consultants June 2011 to Sept 2012
Capacity Development of PMU staff on PDCA  Cycle Aug 2011 to Dec 2017
Development of MIS & GIS System Feb.2012– Nov. 2013
Preparation of extension material Nov. 2011 to Nov. 2014
Training for community motivators June 2012 to Jan. 2016
Baseline Survey    June,2012 June,2012
Mid-term impact assessment September,2015
Terminal impact assessment January,2018
Organization of farmers groups Feb 2012 – Sept. 2015
Training on vegetable cultivation Jan. 2012 – March 2018
Training on food grains cultivation Jan. 2012 – March2018
Promotion of post-harvest technology Jan. 2012 – March2018
First-Priority Sub-projects June-12– Sep.. 2013
Second-Priority Sub-projects Oct. 2012 – Feb 2014
Third-Priority Sub-projects (1st batch) Oct. 2013 – Sept. 2015
Third-Priority Sub-projects (2nd batch) Aug. 2014 – Aug 2016
Third-priority Sub-projects (3rd batch) July 2015 – Aug 2017
Project Completion Date* March 2018